The Federal Government on Thursday expressed satisfaction with the progress of work on the Kaduna-Kano railway corridor, saying the project, including its train stations, has reached a significantly advanced stage and is ready for commissioning.
The Permanent Secretary, Federal Ministry of Transportation, Engr. Funso Adebiyi, stated this during an inspection of the project, after leading officials on a train ride from Jaji in Kaduna State to Kano, where they arrived straight into the terminal station in Kano.
He described the ride as seamless, delightful and extremely commendable, noting that the terminal station was ready, with only the hanging of the station’s name, expected within the next two weeks, outstanding.
The Permanent Secretary recalled that during his last
The Permanent Secretary recalled that during his last visit, he had raised concerns about some aspects of the work, not because the contractors had done badly, but because he saw areas where they could do better, and said those concerns had now been addressed.
One of the major corrections, he said, concerned the glasses to be used in areas where passengers would be. He explained that toughened glasses were no longer used because they can explode when they reach their lifespan or under intensely high temperature. All of them have now been changed to laminated glasses, so that should there be any incident, it hurts nobody, and only the affected section needs to be removed and replaced.
He said he also complained about the lifespan of bulbs used in the stations, insisting that no bulb should have a serviceability lifespan of less than three years. He confirmed that the contractors have complied by changing all the bulbs to meet the specification.
Adebiyi said he also directed the provision
Adebiyi said he also directed the provision of man-lifts to enhance maintenance, and requested the Nigerian Railway Corporation (NRC) to nominate trainable engineers for training on the operations of the stations. He said he would personally sit in class with them, and that only those who pass the examination will remain on the job, to ensure that only serious-minded personnel operate the system.
He disclosed that the Ministry is making a case for a three-month test run of the rail line from Jaji to Kano, possibly on a free service, subject to the approval of President Bola Tinubu, to test the structural integrity of the rail before commercial operations begin.
He said the smoothness of the ride was evident during the inspection, as passengers could drink tea, take soft drinks or eat food without any shaking, and expressed confidence that it will remain so when commercial operations start.
On accessibility, Adebiyi said provision has been made
On accessibility, Adebiyi said provision has been made for persons with disabilities, in line with observations he made during his last visit. He said about four lifts have been ordered for persons with disabilities, while a new staircase has been introduced at the back of the terminal, with railings already imported, designed to enable persons with disabilities to move up and down with ease.
He described the waiting hall as amazing, saying he does not think there will be any terminal in Africa better than the Kano terminal, and expressed satisfaction with the overall quality of work.
On the connection between Kaduna and Kano, Adebiyi explained that Jaji is a security-based area, which posed challenges, forcing the introduction of a horizontal curve that resulted in the construction of a bridge. He said the bridge is to be cast in-situ, meaning it is being constructed on site, and that work on it is at an advanced stage.
He said the bridge is the only thing
He said the bridge is the only thing between the point where they took off and the link to Kaduna, noting that artwork has been done up to the embankment of the bridge, and once it is completed, the rail will be laid. He added that the Kaduna train station where passengers will drop is also undergoing expansion to cope with the resultant traffic from Kaduna.
Adebiyi also disclosed that apart from the Kaduna-Kano line, another line originating from the Kano station to Kazaure, Daura and Katsina is ongoing. He said the team would drive on it the following morning, adding that it has a similar challenge with land acquisition between the station and Dawano, but that from Dawano, the train runs all the way to Kazaure, Daura and Katsina.
On when Nigerians should expect to run from Kaduna to Kano, he said the section from Jaji in Kaduna to Kano is ready, and the remaining short span of barely 10 to 15 kilometres should not take long, assuring that it will be completed within a maximum of four to six months.
He said the Kaduna-Kano corridor has six stations
He said the Kaduna-Kano corridor has six stations in all, broken into three main stations and three sub-stations, in line with the master plan. He explained that the rail actually originated from Apapa in Lagos, from where 40-foot containers can be moved by train to Ibadan, where there is a dry port for clearance.
He added that in the next two months, the Ibadan to Ogun, Ilorin and Minna section will be flagged off, to link to Abuja, while Abuja to Kaduna, Kaduna to Zaria, Zaria to Kano, Kano to Kazaure, Kazaure to Daura and Katsina are being linked, stressing that it is not a piecemeal job but a holistic view of rail construction.
On the Itakpe-Abuja line, Adebiyi said Warri to Itakpe has been completed and is operational, while Itakpe to Abuja is at an advanced stage and is before the President for approval to commence construction, with the procurement process already ongoing. He said when completed, passengers can travel from Warri to Kano, Katsina, Daura and Kazaure, and from Katsina to Jibia and Maradi in Niger Republic.
Speaking during the inspection, the Director-General
Also speaking during the inspection, the Director-General of the Debt Management Office (DMO), Ms. Patience Oniha, said the DMO provides funding and financing for capital projects, and that the visit was to appreciate the work being done with government funds. She said while they drove by road from Kaduna to Kano on their last visit, they travelled by train from Abuja to Kaduna and then to Jaji and Kano without hitches, describing the project as excellent and commending the Ministry of Transportation and the contractors for their commitment.
The Project Coordinator said the team was glad that senior officials visited the site, noting that since commencement, the project has received great support and understanding. He said the Kano station building will be the final venue for the December commissioning, and expressed confidence that with the support of all stakeholders, a wonderful project will be delivered for Nigeria.